HIDE CONTENT
 

Search

CLEAR
İLK CONSTRUCTION// Oil & Gas //Downstream

Gas Treatment Units (GTU) of South Yoloten Gas Field Development Project

  • CLIENTPetrofac International (U.A.E.)
  • LOCATION Turkmenistan / Yoloten / Mary
  • STATUS Completed Projects
  • SCOPE OF WORKS
  • Engineering, Procurement, Installation and Commissioning of 4 nos Gas Treatment Units each has 5 BCMA capacity natural gas primary treatment system.

PROJECT DETAILS

Main Products

Piping

172.464 dia-inch (includig CS; LTCS; Incoloy and Stainless Steel)

Steel Structure

2.573 tons

Grating & Chequered Plate

6.300 m²

Equipment

4.625 tons

Equipment Insulation

3.560 m² 

Piping Insulation

31.297 m²

E&I works

 

Pipe Painting & Coating

36.321 m²

Passive Fire Protection

18.000 m²

 

Information Society Services