Search
- LOCATION
- PROJECT STATUS
- CLASSIFICATION
- CLIENT
- Dragon Oil Ltd.19
- Petronas Carigali (Turkmenistan) Sdn. Bhd.7
- Petronas Carigali (Turkmenistan)Sdn. Bhd, MMHE – Technip J.V.2
- Hyundai Engineering Co., Ltd.3
- Botaş1
- Turkmen Gas / Hyundai Eng. Ltd.1
- Petrofac International (U.A.E.)4
- Petronas Carigali (Turkmenistan) Sdn. Bhd., MMHE Technip J.V. - Sumatec1
- Gilan Holding LLC2
- Administration of The President Turkmenistan5
- Pasha Construction7
- Thales Alenia Space - CIFAL FZCO1
- State Committee On Property Issues of The Republic of Azerbaijan1
- Azersu QJSC1
- -1
- Oil & Gas Trust SOCAR1
- Pasha Holding1
- Daykhan Bank State Commercial Bank of Turkmenistan1
- Central Bank of Turkmenistan1
- Ministry of Railway Transportation of Turkmenistan1
- Ural Garant1
- Land Development Project3
- JGC Construction Co.2
- CAI Interbudmontaz1
- ODD Uralyevrostil1
- Public Corporation Prodim1
- Turkmen Gas / Petrofac Int. (U.A.E.)1
- The State Commodity and Raw Material Exchange0
- Stroy Zakas1
- TSGI Mühendislik Insaat Ltd. (Técnicas Reunidas, Saipem and GS Consortium)1
- Aikon Construction MMC.1
- Baku Bus Limited Liability Company1
- Qaiwan Group1
- Azeravtoyol Asc1
- Eremtas1
- ILK CONSTRUCTION4
- Highland City1
- CPI Power Engineering Co., Ltd.1
- Arab Potash Company Ltd.1
- People's Democratic Republic of Algeria Ministry of National Defence1
- PKN ORLEN0
Turkmenistan Gas Desulfurization Project
- CLIENTTurkmen Gas / Hyundai Eng. Ltd.
- LOCATION Turkmenistan / Yoloten / Mary
- STATUS Completed Projects
- SCOPE OF WORKS
- Civil, Architectural and HVAC works, Building Works, Tank & Silo Installation Works, Soil Investigation Works, Underground Piping Installation & Painting Works, Temporary Access Road to Site, NDE and PWHT work, Temporary Camp Facilities, Manpower & Equipment Supply of Scaffolding Works.
PROJECT DETAILS
Main ProductsCivil, Architectural and HVAC works | |
Earthworks | 261.915 m³ |
Concrete | 44.915 m³ |
Reinforcement | 4.217 tons |
Piling Works | 610 Nos 600 mm dia, 20 m length piles |
Pile Testing Works | Compression, Lateral, Tension Load and Integrity tests |
Building Works | |
Control Building |
1.035 m² |
Instrument & Substations Buildings | 3.196 m² |
Fire Water Pump Building | 252 m² |
Emergency Diesel Generator Building | 163 m² |
Demineralized Water Package Building | 81 m² |
Gate Houses | 180 m² |
Solid Sulfur Warehouse | 6.000 m² |
Sulfur Solidification Package Shelter | 1.320 m² |
Treated Gas Compressor Shelters | 432 m² |
HVAC Works | HVAC Equipment, Duct. |
Chilled/Cooling water Piping, Drainage, Plumbing, | |
Potable-Hot Water Piping, Sanitary Piping, HVAC Control, Instrumentation. | |
Tank & Silo Installation Works | 13 each total 1.197 tons tanks and 4 each total 150 tons silos. Fabrication, erection, installation, painting, NDT and hydro test of tanks and silos, commissioning. |
Soil Investigation Works | |
Boreholes, sampling, in-situ and laboratory testings |
|
Bore Hole Drilling | 67 nos |
Trial Pit | 5 nos |
In-Situ Testing | Electrical resistivity, SPT, Plate Load tests etc |
Laboratory Testing | Soil classification, Chemical analysis, |
Compaction Test, CBR, Permeability etc. | |
Underground Piping Installation & Painting Works | 68.302 dia-inch RTRP and CS Underground Piping with installation of 14.214 each flange, valve etc., 162.000 m² blasting and painting, hydro testing, commissioning. |
Temporary Access Road to Site | Design and Construction of 7.2 km length and 11 mt width temporary access road. |
Main Products | |
Total Length | 7.2 km |
Width | 11 m |
Stripping | 187.000 m² |
Cutting | 350.000 m³ |
Filling | 236.000 m³ |
Sub-Grade (90% compaction & CBR > 30) | 113.000 m² |
Base Course (with compaction, thickness 150 mm) | 17.000 m³ |
NDE and PWHT work | Post Weld Heat Treatment, Hardness, Radiographic, Ultrasonic, Liquid Penetrate, Magnetic Particular&PMI tests. |
Main Products | |
PWHT joints | 32.098 nos – 230.402 dia-inch |
Hardness Joints | 32.098 nos PMI joints : 100 nos |
RT joints | 14.998 nos – 177.000 sheet films |
PA UT joints | 5.756 nos – 65.000 diainch |
MT joints | 24.152 nos – 62.266 diainch + 538 m |
PT joints | 8.516nos – 12.960 diainch |
Vacuum | 1.838 m |
Temporary Camp Facilities | Site preparation, civil works, building installation, electrical and mechanical infrastructure works for camp and workshop area prefabricated buildings 3.000 Person capacity. |
Main Products | |
Total Open Area : 280.000 m² | |
Closed Area : 48.635,14 m² | |
Manpower & Equipment Supply of Scaffolding Works | Supply all competent labours and services, consumables, equipment and tools, utilities, surveys, tests and supervisions for scaffolding Work. |